Enter each element of the operator's routine with its manual, walk and machine time. The chart lays them out against takt, and the checks show whether the station keeps pace and where people or machines wait.

ON THE EXAM · CQE V.D.6, V.D.7, CSSBB VII.B.1, CSQP IV.A.3, CMDA V.B.3 · FREE · NOTHING YOU TYPE LEAVES YOUR BROWSER

Q-BotClick for an explanation of this tool.

For educational use. This page is a study aid. The method behind it has far more depth and detail than one page and one tool can cover, and what you see here is not everything the method offers or everything this site offers. For full understanding and application, use the governing standards and texts, and seek further education, training or qualified advice. Results depend on the data you enter, so check them before relying on them.

What the combination sheet shows

Standardized work is the current best way to do a job, written down: the sequence of elements, the time each takes, and the stock needed to keep it flowing. The combination sheet (the standardized work combination table) is the part that shows how a person's work and the machines' work fit together over one cycle. It is the tool for designing work in a cell where one operator runs several machines.

The three kinds of time

The operator's cycle is the sum of manual and walk time. Machine time runs in parallel with the rest of the routine.

Takt and cycle time

Takt time = available time ÷ customer demand. With 440 available minutes and a demand of 330 units a shift, takt is 80 seconds: the station must finish one unit every 80 seconds. Takt comes from the customer; it is not a measure of the process. The value stream map calculates it for the whole family.

A machine must finish its run before the operator comes back to it, one cycle later. If a machine's load time plus run time is longer than the operator's cycle, the operator waits at that machine. The station's cycle time is therefore the longer of the operator's cycle and the longest machine cycle. That is the number to compare with takt.

Reading the chart

Time each element several times and use the lowest repeatable time, not an average that includes interruptions. The interruptions are problems to solve, not part of the standard.

On the exam

Standardized work and takt time are lean tools in the CQE Body of Knowledge (V.D.6 and V.D.7). The CSSBB includes standard work under waste elimination (VII.B.1), the CSQP lists standardized work and takt time (IV.A.3), and the CMDA names standard operations among the lean tools (V.B.3). Expect to calculate takt time, compare cycle time with takt, and say what to do when a station is over takt.