Lessons learned register

SCQUALITYGUILD.COM/TOOLS/LESSONS-LEARNED-REGISTER.HTML

Close out a project with results against goal, schedule and cost, a register of lessons with owners and recommendations, and a plan for moving the knowledge to the people who need it.

ON THE EXAM · CMQ/OE III.A.7, III.C.4 · FREE · NOTHING YOU TYPE LEAVES YOUR BROWSER

Q-BotClick for an explanation of this tool.

For educational use. This page is a study aid. The method behind it has far more depth and detail than one page and one tool can cover, and what you see here is not everything the method offers or everything this site offers. For full understanding and application, use the governing standards and texts, and seek further education, training or qualified advice. Results depend on the data you enter, so check them before relying on them.

Why lessons learned fail

Most organizations hold a lessons-learned meeting at the end of a project. Fewer change anything because of it. The usual pattern is a document filed on a shared drive, written in general terms, with no owner and no change to how the next project is run. A lesson is learned only when behavior or the system changes: a procedure, a template, a checklist, a training plan, or the way a team works.

Tacit and explicit knowledge

Explicit knowledge can be written down and shared through documents, procedures and databases. Tacit knowledge lives in people: judgment, skill, know-how and relationships that are hard to put into words. Nonaka and Takeuchi's SECI model describes four ways knowledge moves:

The trap is to treat all knowledge as explicit. A procedure update will not transfer a senior technician's judgment; mentoring or a community of practice will.

Barriers to sharing

Common barriers are a blame culture (people hide what went wrong), lack of time at project close, no place to find past lessons, the belief that each project is unique, and knowledge treated as personal power. Leaders lower them by asking for what went well as well as what went wrong, by keeping the review about the process rather than the people, and by visibly acting on what is recorded.

The close-out summary

Project closure confirms that deliverables were accepted, compares results with the goal in the charter, reports schedule and cost against plan, releases the team, hands remaining work to an owner, and archives the project documentation. The lessons register belongs in that package and should be searchable by the next project manager.

On the CMQ/OE exam

Expect to tell tacit from explicit knowledge, to match a SECI stage to an activity, and to choose the best way to make a lesson stick.