Engineering change impact checklist

SCQUALITYGUILD.COM/TOOLS/ENGINEERING-CHANGE-IMPACT-CHECKLIST.HTML

For one engineering change: list everything it touches, from the drawing to the stock at the customer, with an owner, an update and a check for each. Set the effectivity, decide what happens to existing stock, and see what is still open.

ON THE EXAM · CQPA I.B.6, CQE II.B.2, CQE IV.B.1, CSQP IV.C.2, CSQP V.A.3, CMDA III.D.2, III.D.3 · FREE · NOTHING YOU TYPE LEAVES YOUR BROWSER

Q-BotClick for an explanation of this tool.

For educational use. This page is a study aid. The method behind it has far more depth and detail than one page and one tool can cover, and what you see here is not everything the method offers or everything this site offers. For full understanding and application, use the governing standards and texts, and seek further education, training or qualified advice. Results depend on the data you enter, so check them before relying on them.

Why changes go wrong

Most engineering changes that cause trouble were approved correctly. The drawing was updated and signed. What went wrong was something nobody connected to the change: the control plan still checked the old tolerance, the machine still ran the old program, the gauge could not resolve the new limit, 800 old-revision parts sat in finished goods, or the customer was never told. The change was right; the implementation was incomplete.

This checklist is for that second part. It lists every document, plan, program, record and stock location the change could touch, and asks for a yes or a no on each, an owner, the date it was updated and the date someone else checked it.

Configuration management

Configuration management is the discipline of knowing, at any time, exactly what a product is made to: which drawing revision, which specification, which software version, which bill of materials. It has four parts:

Document control keeps the right revision at the point of use. Configuration management goes further: it keeps the whole set of documents, programs and parts consistent with each other.

Effectivity and interchangeability

Effectivity is the point from which the change applies: a date, a serial number or a lot. Date effectivity is simple but blurs when stock is built ahead. Serial or lot effectivity is precise, and is what makes a later recall or field action small. Either way, the new revision must be identifiable on the part or its paperwork.

Interchangeability decides what can happen to old stock. If old and new parts are fully interchangeable, old stock can usually be used up. If the change is one-way, new parts can replace old in service but not the reverse. If they are not interchangeable at all, old and new must never be mixed in an assembly or a shipment, and old stock is reworked, scrapped or kept only for older products.

Reading the checks

For a change that also needs people to change how they work, pair this with the change management plan. For the control plan itself, use the control plan tool.

On the exam

CQPA I.B.6 asks you to identify the elements of document control systems, including configuration management. CQE II.B.2 asks you to evaluate configuration management, maintenance and document control, and CQE IV.B.1 covers material identification, status and traceability, which is what effectivity and stock disposition depend on. CSQP IV.C.2 includes updating the FMEA and control plan and product or process design change with a supplier, and CSQP V.A.3 covers change requests and notifications. CMDA III.D.2 covers design changes, and III.D.3 the document and change control system.